But the only record that seems certain to break for ITER won’t be to “burn” the plasma at temperatures 10 times higher than the sun’s core, keeping this “artificial star” in flames and producing net fusion energy all at once. Instead, ITER is on the verge of an unwelcome record, with accumulated schedule slippage and budget overruns threatening to make it the most overdue and costliest science project in history.
17 years on and the costs are out of control
The ITER project officially began in 2006, when its international partners agreed to finance an estimated €5 billion ($6.3 billion at the time) 10-year plan that would enable ITER to become operational in 2016. According to the latest official information, the cost was over an estimated €20 billion ($22 billion), with ITER less than two years into operation. However, documents recently obtained through a lawsuit show that these figures are unfortunately out of date. Delays and additional costs are not just a few years and a few billion dollars, but are completely uncertain.
It was scheduled to open in 2025
Not only did some components of ITER fall far behind schedule, some of these machines also turned out to be flawed. In November 2022, the ITER Organization decided not only to stop the assembly of the vacuum vessel, but also to disassemble the already assembled part for repair. During this period, France even decided to stop the construction of ITER due to security concerns. While this legal process was going on, it came to the fore that additional barriers could be added to ITER to ensure radiation safety. But it’s unclear whether the foundations of the plant will lift them. A current cost report has not been made available to the public yet.
ITER isn’t the only major scientific project delayed
But ITER and JWST are not remotely the same. The origins of ITER can be traced back to a handshake agreement between Ronald Reagan and Mikhail Gorbachev in the mid-1980s – and the cost is higher than any scientific work in history. Adjusted for inflation, the cost is about the same as the Manhattan Project ($25 billion), which built the first atomic bombs, and will almost certainly increase.
And unlike the JWST, which was fully operational only a few months after launch, ITER will not be fit for purpose even years after construction is complete. ITER’s main goal of performing high-power fusion experiments using a mixture of the heavy hydrogen isotopes deuterium and tritium won’t happen until more than a decade after the machine reaches its first plasma milestone. As a result, no one can say exactly when the construction of the ITER project will be completed, what the costs and delays are. The process can take “generations,” according to Scientific American.